Sooke Lake Road Low Pressure Sewer
The Opportunity
West Shore Environmental Services extended approximately 225 m of low pressure sanitary sewer from the existing sanitary sewer manhole fronting 2832 Sooke Lake Road to the east end of Sooke Lake Road in the City of Langford.
The Approach
West Shore Environmental Services extended approximately 225 m of low pressure sanitary sewer from the existing sanitary sewer manhole fronting 2832 Sooke Lake Road to the east end of Sooke Lake Road in the City of Langford. The project was driven by the need to connect the Goldstream Mobile Home Park at 2847 Sooke Lake Road to sewer as the existing septic fields were beginning to fail.
Westbrook Consulting Ltd. provided topographic survey, detailed civil engineering design, tendering, and construction layout and inspection services for the extension. Throughout the project, coordination was required with West Shore Environmental Services, the City of Langford, and the contractor.
A challenge of the project was to complete the work in a tight time frame to ensure the mobile home park could be connected before the septic fields failed.
The construction of the sewer main was completed in August of 2017.
Key Personnel: Ryan Deernsted